Program
Management
REPORT CARD

MOBILE
COUNTY
SCHOOL SYSTEM
$350 Million Building Program |
Volket & Associates, Inc., can provide turn-key
services by offering its program management concepts to your
school system.
This means
we’ll oversee the entire process, from selecting the architect,
coordinating the construction, to providing all necessary
financial reports. And,
our track record proves we can achieve project delivery on or
below budget.
Volkert is in the top one
percent of all engineering and architectural design firms in the
nation and one of the ten fastest growing design/consulting firms |
|
|
PHASE
I BUILDING PROGRAM
|
|
Assignment
|
Budget
|
Contract
|
|
Allentown
Elementary
|
$ 4,200,000
|
$ 4,107,000
|
|
Alma
Bryant High School
|
$12,000,000
|
$11,947,300
|
|
C.
H. Burns Middle School
|
$ 5,800,000
|
$ 5,809,000
|
|
Calcedeaver
Elementary School
|
$ 700,000
|
$ 613,084
|
|
Calloway
Smith Middle School
|
$ 5,100,000
|
$ 5,416,565
|
|
Dodge
Elementary School
|
$ 1,650,000
|
$ 1,511,777
|
|
Ella
Grant Elementary School
|
$ 3,600,000
|
$ 4,072,036
|
|
Griggs
ElementarySchool
|
$ 1,500,000
|
$ 1,391,660
|
|
Hollinger’s
Island Elementary School
|
$ 700,000
|
$ 636,087
|
|
Florence
Howard Elementary School
|
$
4,800,000
|
$ 4,986,787
|
|
Lee
Elementary School
|
$ 700,000
|
$ 615,912
|
|
Orchard
Elementary School
|
$ 1,000,000
|
$ 1,034,021
|
|
Semmes
Elementary School
|
$ 4,200,000
|
$ 4,072,100
|
|
Spencer
Elementary School
|
$ 2,700,000
|
$ 3,020,888
|
|
INCREASE
WITHOUT ADDITION TO BUDGET
|
|
Energy
Management Systems
|
|
-$ 779,838
|
|
Computer
Technology
|
|
-$ 363,688
|
|
Multipurpose
Rooms @ Eight Schools
|
|
-$ 3,600,000
|
|
TOTAL
OF VALUE ADDED ITEMS
|
|
-$
4743,526
|
|
SUBTOTAL
|
$48,650,000
|
$44,491,091
|
|
DEDUCT
FOR TAX CREDIT
|
|
-$ 1,482,144
|
|
PROGRAM
TOTAL
|
$48,650,000
|
$43,008,947
|
|
|
PHASE
II BUILDING PROGRAM
|
|
Assignment
|
Budget
|
Contract
|
|
Baker
II Elementary School
|
$ 5,400,000
|
$ 5,293,578
|
|
Citronelle
Elementary School
|
$ 9,120,000
|
$ 9,026,039
|
|
Craighead
Elementary School
|
$ 5,605,000
|
$ 5,291,500
|
|
Dauphin
Island School
|
$ 580,000
|
$ 620,799
|
|
Davidson
High School
|
$ 6,400,000
|
$ 6,378,900
|
|
Dixon
Elementary School
|
$ 1,010,500
|
*
$ 1,010,500
|
|
Dodge
Elementary School
|
$ 1,800,000
|
*
$ 1,800,000
|
|
E.
R. Dickson Elementary School
|
$ 1,800,000
|
*
$ 1,800,000
|
|
Fonde
Elementary School
|
$ 1,800,000
|
*
$ 1,800,000
|
|
Forest
Hill Elementary School
|
$ 4,200,000
|
$ 4,222,320
|
|
Hutchens
Elementary School
|
$ 5,00,000
|
$ 4,901,000
|
|
Mertz
Elementary School
|
$ 5,400,000
|
$ 5,230,000
|
|
Montgomery
High School
|
$ 3,000,000
|
$ 2,500,775
|
|
Semmes
Middle School
|
$ 9,00,000
|
$ 9,844,449
|
|
Westlawn
Elementary School
|
$ 4,150,000
|
$ 4,072,179
|
|
Williams
Elementary School
|
$ 750,000
|
$ 786,427
|
|
ESTIMATED
TAX CREDIT
|
|
-$ 2,208,584
|
|
PROGRAM
TOTAL
|
$65,015,000
|
$62,369,882
|
|
|
|
|
|